Skip to main content

Current Construction Projects News:

The stairs have been installed at our custom home in Glenview »

July 8, 2019

We are using an luxury vinyl plank (LVT) in the basement over radiant heated floors in Glenview »

July 1, 2019

We have laid the asphalt on our driveway at our spec house »

June 28, 2019

There is a front side walk to the house and more trees at 511 North Branch »

June 22, 2019

The front stoop is done and we will work on the sidewalk next at our new construction in Glenview »

June 15, 2019

The driveway is being prepped for asphalt at North Branch in Glenview »

June 13, 2019

The landscaping and paver work has start on our new construction in Glenview »

June 10, 2019

We have added a pergola over the garage at 511 North Branch in Glenview »

May 23, 2019

The drywall is done and we are getting ready to prime at our spec house in Glenview »

May 22, 2019

The insulation should be completed in the next few days and next will be drywall at our new construction in Glenview. »

May 2, 2019

The bead board is in the ceilings in the front porch and in the four season room at 511 North Branch in Glenview »

May 1, 2019

We will be staining these ceilings to match the front door.

We have started the siding and column work at our spec house in Glenview »

April 26, 2019

Installed brick in the window wells and limestone caps on top in Glenview »

April 21, 2019

We are starting a new commercial project at the BP Gas station on Belvidere in Waukegan »

April 12, 2019

We will be putting a small addition on the back of the building along with creating a mini-mart inside.

The four season room has been framed and is ready to be finished at our custom home in Glenview »

April 9, 2019

9

The stoops, generator pad, air conditioner pad and have been poured at our spec house in Glenview »

April 5, 2019

The basement is framed at our new construction on North Branch in Glenview »

March 28, 2019

We used GAF Woodland roofing shingles on the spec house on North Branch in Glenview »

March 22, 2019

The basement slab has been poured in Glenview »

March 20, 2019

The Valder’s Stone has been installed at our new construction in Glenview »

March 16, 2019

The rough HVAC, electrical and plumbing work has started at our spec house at 511 North Branch in Glenview »

March 12, 2019

The Pella windows are being installed at our spec house in Glenview »

February 12, 2019

The roofing felt paper has been installed at our spec house on North Branch in Glenview »

February 9, 2019

The roof sheathing is done and we are ready for felt paper on our spec home in Glenview »

February 8, 2019

The roof framing at 511 North Branch in Glenview has almost been completed »

February 4, 2019

We are framing the roof on our spec house on North Branch in Glenview »

February 1, 2019

The 2nd floor walls are going up at our spec home in Glenview »

January 25, 2019

The sub floor is being installed on the 2nd floor of our spec house at 511 N. Branch in Glenview. »

January 24, 2019

The first floor walls are up we are ready to move to the second floor on North Branch in Glenview. »

January 21, 2019

The first floor decking and walls are going up on our new construction on Branch in Glenview »

January 15, 2019

Running the storm sewer line for our new spec house in Glenview »

January 3, 2019

Running the new water service to the spec house on North Branch in Glenview »

December 28, 2018

Starting the Build Out of Hollywood Trendz Hair & Spa in Addison »

December 18, 2018

Starting the Build out of Four Seasons Steak & Grill in Addison »

December 18, 2018

Starting the Build out of New York Chaat in Addison »

December 18, 2018

Starting the Build out of Alara Designer’s Boutique in Addison »

December 18, 2018

The steel has been installed at 511 North Branch in Glenview »

December 14, 2018

We used the Graywall product at our new spec house on Branch in Glenview »

December 10, 2018

The Graywall product is a rubber membrane that is sprayed on the foundation walls as a foundation waterproofing by Westside Rub-R-Wall Inc.

Removing the forms on the foundation walls at North Branch in Glenview »

December 7, 2018

Pouring the Foundation walls at our spec house in Glenview »

December 5, 2018

Setting up the forms for the foundation walls at North Branch in Glenview »

December 4, 2018

We are pouring the concrete for the footings at the spec house in Glenview »

November 21, 2018

We are framing the footings at Branch in Glenview »

November 20, 2018

Excavation continues at the new construction in Glenview »

November 16, 2018

Excavation has started on our spec house on Branch in Glenview »

November 14, 2018

Removing the old foundation on our spec house at 511 N. Branch in Glenview »

November 9, 2018

The cabinets are being installed in the kitchen at Kilbourn in Skokie »

November 9, 2018

Demolition has begun for our spec house in Glenview »

November 8, 2018

Construction fencing is up and demolition will begin soon at our spec house in Glenview »

October 19, 2018

The front door and roof gable has been completed at Kilbourn in Skokie »

October 18, 2018

Besides the drywall and insulation we have to remove everything that got water damage after the fire in Chicago »

October 18, 2018

We are cleaning the brush around the house on Branch in Glenview. »

October 18, 2018

We have cut the trees and removed the bushes around the house before we start demolition.

Starting to gut the 2nd floor of the house to remove all drywall and insulation from the fire damage in Chicago »

October 15, 2018

We will be starting repairs on this fire damaged house in West Roger’s Park Chicago »

October 13, 2018

Closing up the old entrance and making a new entrance to the service corridor at Shalimar Plaza Addison »

October 11, 2018

Hardwood floors are being installed at our addition in Skokie »

October 11, 2018

The tile work has begun at our addition in Skokie »

October 5, 2018

The sidewalk in front of Shalimar Plaza is being framed and prepped so that we can pour concrete in Addison »

September 28, 2018

The rough plumbing is done for the Hollywood Trendz Hair Salon build out in Addison »

September 25, 2018

Underground plumbing work for the bathrooms and sanitary at our commercial build outs in Addison »

September 24, 2018

Underground plumbing work has started for the kitchen in Four Seasons Steak & Grill in Addison »

September 19, 2018

We are installing the grease trap in the kitchen

We are excavating for the parking lot in front of Shalimar Plaza »

September 12, 2018

We have started framing Alara Designer’s Boutique at Shalimar Plaza in Addison »

September 3, 2018

The curbs are being poured at Shalimar Plaza in Addison »

August 31, 2018

Drywall has been hung, taped and primed at the addition on Kilbourn in Skokie »

August 27, 2018

The curbs are being framed and prepared for concrete at Shalimar Plaza in Addison »

August 23, 2018

We have started framing Hollywood Trendz salon and the service corridor in Addison »

August 23, 2018

The underground plumbing has been inspected and we have poured the concrete for the salon build out »

August 22, 2018

Masonry work and landscaping done at our addition in Skokie »

August 21, 2018

The exterior facade is complete on Elmhurst Rd in Des Plaines »

August 20, 2018

The parking lot elevations have been marked and we are getting ready to excavate in Addison »

August 17, 2018

Community Animal Rescue Efforts has been completed and is ready for Adoptions in Skokie »

August 16, 2018

The Address is 4927 Main Street in Skokie.

Running the sanitary lines from inside the building to the sanitary manholes at our Commerical project in Addison »

August 10, 2018

Installing the sanitary manholes at our commercial store build outs in Addison »

August 7, 2018

The sanitary manholes are being delivered for our commercial job in Addison »

August 6, 2018

The exterior signs and lights are up on the Animal Rescue on Main St. in Skokie »

August 4, 2018

New Commercial Salon Build out will be starting soon in Addison »

July 30, 2018

We will be starting the build out of the Hollywood Trendz Hair & Spa at their new location in Shalimar Plaza in Addison.

New roof over front door at the addition on Kilbourn in Skokie »

July 18, 2018

The owners have decided they want an roof overhang over the front door.

We are using Closed Cell spray foam insulation at Kilbourn in Skokie »

July 17, 2018

Drywall work is done at our commercial facade on Elmhurst Rd in Des Plaines »

July 11, 2018

Starting to access the damage and start the restoration process after the fire in Skokie »

June 28, 2018

The fire started in the kitchen and spread.  The first step was to call Simon at Rainbow Restoration in Skokie to have him come in to find out what of the personal belongings could be salvaged.

Spray foam insulation was used in the exterior walls at the commercial job in Des Plaines »

June 29, 2018

A solar hot water system was installed at the Animal Rescue in Skokie »

June 25, 2018

The solar system should roughly produce 200 gallons of hot water per day or 80,000 gallons per year.  Since animal rescue facilities use so much hot water this will help with saving heating costs.

 

 

 

 

 

Soon we will be starting repairs on this fire damaged house in Skokie »

June 25, 2018

From the outside you can’t tell that this house has had a fire.

Alara Designer’s Boutique under ground plumbing has been completed and is being prepped to pour the concrete in Addison »

June 25, 2018

The salon underground plumbing is being prepped before pouring the concrete at our commerical buildout in Addison »

June 21, 2018

The front door awning is going up at C.A.R.E. on Main St in Skokie »

June 20, 2018

We are bringing the water lines to our 8 storefronts in Addison »

June 15, 2018

We are bringing the water lines from the City main to each of the store fronts.

The metal roof has been installed on the commercial facade in Des Plaines »

June 15, 2018

We are putting in a utility vault for the water tap at 260-274 W. North Ave in Addison »

June 6, 2018

A utility vault is an underground room providing access to the water line and valves that are connected to the City main line

The underground pvc has been laid for Hollywood Trendz Hair & Spa in Addison »

June 5, 2018

The PVC for the bathroom, pedicure chairs and laundry room are done

We are preparing the basement walls for insulation at the addition in Skokie »

June 1, 2018

The EIFS is done at the Commercial job on Elmhurst in Des Plaines »

June 1, 2018

We have installed EIFS ( Exterior Insulation and Finish System) on the exterior of the facade and gave it a stucco like texture.  Next step will be to install the metal roof.

 

The counter tops and laundry room sink have been installed at C.A.R.E. animal rescue in Skokie »

May 23, 2018

The underground plumbing work has started at Alara Designer’s Boutique in Addison »

May 22, 2018

We have started cutting the concrete for the underground plumbing at Hollywood Trendz Hair Salon in Addison »

May 22, 2018

Finished the flat work at our Addition in Skokie »

May 18, 2018

We poured the concrete sidewalks and patio slab.

Windows are installed on the Commercial facade in Des Plaines »

May 18, 2018

We installed new Pella Impervia line fiberglass commercial windows.  We are ready to start the stucco.

New Water Service for our addition in Skokie »

May 16, 2018

We have to bring a new water line in from the City main to the house for the addition.

Patio slab and side walks are being prepped at our addition on Kilbourn in Skokie »

May 10, 2018

We are putting down the stone and wire mesh to prep the patio slab prior to pouring the concrete along with prepping the sidewalks.

Contact Request





News Reviews FAQ Site Map Login