Skip to main content

Current Construction Projects News:

The rough carpentry has been completed on the commercial facade »

April 17, 2018

Installing roof felt paper at the commercial facade in Des Plaines »

April 11, 2018

Working on the exterior of the facade at our commercial project »

April 7, 2018

We are wrapping the exterior of the facade with densglass fiberglass mat sheeting and will then put two layers of tyvek wrap to protect the exterior walls.

We have begun to frame the exterior wall for the new facade in Des Plaines »

April 5, 2018

We have started to frame the walls for the new enclosed 2nd floor walkway.

The exterior demolition has begun at our addition on Kilbourn in Skokie »

March 29, 2018

Demolition has started on the commercial facade on Elmhurst in Des Plaines »

March 28, 2018

The demolition has started and the framing materials are being delivered for the new facade at 969 Elmhurst.

The interior demolition has started on our addition in Skokie »

March 27, 2018

Grinding the concrete Floors before applying epoxy at C.A.R.E. »

March 27, 2018

We are going to be starting an addition on Kilbourn in Skokie! »

March 24, 2018

The Facade work has been completed at Teddy Rose and America’s Custom Home Builders. »

March 20, 2018

Interior Concrete work at C.A.R.E. in Skokie »

March 9, 2018

The concrete pad has been poured in the mechanical room for the water heaters and the concrete pad for the dog kennels are done.

Ready for priming at our Animal Rescue commercial build out in Skokie »

March 8, 2018

The taping and mudding has been done and we can prime the new walls.

We are backfilling the grade beam with gravel at our commercial job in Addison! »

March 6, 2018

We have started to drywall the Community Animal Rescue Effort new facility. »

March 5, 2018

There has been additional insulation added between some of the walls for sound proofing.

Planned Commercial Facade Renovations at 969 Elmhurst Rd in Des Plaines to start soon »

March 5, 2018

We will be starting a new project to change the facade of this building to enclose the 2nd floor walk way in the next couple of weeks.

New Spec Home at 511 N. Branch in Glenview coming Soon! »

February 25, 2018

We are in the process of purchasing this 2/3’s of an acre lot in Golf Acres.  We will share elevations and plans shortly.

The forms have been removed and the grade beam is starting to cure in Addison »

February 23, 2018

We are pouring the concrete for the grade beam at Shalimar Plaza in Addison »

February 22, 2018

The Spec Home has been sold and the new owners have moved in. »

February 22, 2018

View Completed Project Gallery

The grade beam is ready for concrete at our commercial job in Addison! »

February 19, 2018

We have put up the concrete forms and have laid all of the rebar and are ready to have the concrete trucks line up tomorrow.

The grade beam footing has been poured in Addison »

February 14, 2018

The footings are being framed for the grade beam at our commercial job in Addison. »

February 13, 2018

The grade beam is a reinforced concrete beam that sits on the caissons to spread the load of the building.  This footing gives the grade beam something level to sit on.

The fire sprinkler system piping is being installed at C.A.R.E. »

February 13, 2018

We have finished framing the walls and doors at Community Animal Rescue Effort in Skokie »

February 8, 2018

The catio’s have also been framed.

The Drywall and Drop ceilings are done at Teddy Rose Hair Salon & Day Spa on Oakton in Skokie »

February 3, 2018

The ceiling has been finished along with the lighting and heating ducts.

We have started the heating and A/C duct work at C.A.R.E. in Skokie. »

January 31, 2018

We are putting a roofing membrane on the parapet wall! »

January 30, 2018

We are installing a roofing membrane on the parapet wall to protect the commercial building from water penetrating the roof.

The framing of the new facade has been completed! »

January 30, 2018

We are framing the new store fronts for Teddy Rose and America’s Custom Homes! »

January 29, 2018

We are framing the parapet walls and new store fronts for Teddy Rose and America’s Custom Home Builders.

The dog kennels have been built at our commercial animal shelter build out. »

January 25, 2018

We have built the walls for the dog kennels for the Adoption Center at C.A.R.E. in Skokie.

We are installing caisson piers for added support at Shalimar Plaza in Addison. »

January 23, 2018

We had to drill 12 feet down in the ground, install a lot of rebar and then pour concrete to give the front of the building the necessary support.

The concrete has been poured over the underground plumbing at C.A.R.E. in Skokie »

January 9, 2018

The concrete has been patched after the underground plumbing work had been done.

The underground plumbing work as begun at Community Animal Rescue Effort’s in Skokie »

January 5, 2018

The underground plumbing for the sinks and trench drains around the dog kennels has been started.

Our Spec House at 937 Echo Lane in Glenview is under Contract! »

December 30, 2017

We are closing at the end of January.

New Glass block windows have been installed at the Community Animal Rescue Effort in Skokie »

December 22, 2017

Interior Framing for the Commerical facades on Oakton in Skokie! »

December 17, 2017

We had to add additional support to the current roof joists to support the new store fronts for Teddy Rose and America’s Custom Home Builders.

New Dog Exercise Area and garbage enclosure fencing at C.A.R.E. in Skokie »

December 8, 2017

Demo has begun in creating a new look for Teddy Rose and ACH! »

December 8, 2017

We have had the ceiling tiles and drywall removed along to get prepared for adding additional support to the front on the building to support a new facade and parapet wall.

 

The spec home has been completed in Glenview and is back listed on the market! »

November 28, 2017

We have installed the new flat roof on Shalimar Plaza in Addison. »

November 24, 2017

The existing roof was torn off and a new TPO flat roof was installed on the new strip mall.

 

 

We will be starting a new Commercial Facade Project in Skokie »

November 14, 2017

We will be giving Teddy Rose Hair Salon and Day Spa and America’s Custom Home Builders a new look over the next few months.

The parking lot is done at our commercial job in Skokie »

November 15, 2017

The parking lot has been paved and the parking lot strips have been painted.  Now we w need to wait at least 7 days before driving on the new asphalt.

We are paving the parking lot at C.A.R.E. in Skokie »

November 15, 2017

Temporary Shoring is needed before we can go forward with excavation at Shalimar Plaza »

October 25, 2017

We have added temporary shoring at each end of the warehouse and are adding additional lateral support to the outside walls before we can excavate.

The 2nd Porch has been completed at Western Ave. in Chicago! »

October 16, 2017

The granite and quartz has been installed in the bathrooms at Echo in Glenview »

October 13, 2017

We have installed the Closet Systems at our New Construction at Echo in Glenview »

October 11, 2017

The concrete work has been completed at Community Animal Rescue Efforts, Inc. in Skokie! »

October 6, 2017

The Kitchen Cabinets have been installed at our Spec House In Glenview »

October 6, 2017

The curbs have been framed at our commercial job in Skokie »

October 5, 2017

We are removing the existing parking lot at C.A.R.E in Skokie! »

October 4, 2017

The water service is done and setup inside the C.A.R.E. building. »

October 3, 2017

The new water service is inside the building and we are back filling where we ran the new water lines from the street to the building with stone.

Bringing the new water line from the main in the street to the building at 4927 Main St. Skokie »

October 2, 2017

The concrete vault has been installed to protect the valve at the water main in the street, we have brought the water line to the building and are digging inside the building to install the new water line.

 

Water and Storm work continues at our commercial project in Skokie »

September 30, 2017

We have tapped into the main water line across the street and are bringing the new water line to the building.

 

We have started framing the walls at C.A.R.E. »

September 29, 2017

Demolition has been completed and we have started to frame new walls.

We are installing the kitchen cabinets in our spec house in Glenview »

September 29, 2017

Civil work has begun at Community Animal Rescue Efforts, Inc. in Skokie »

September 27, 2017

We have started the storm work to replace two existing sinking storm basins in the parking lot.

We have tuck pointed our Commercial project in Skokie »

September 25, 2017

 

Tuck pointing and power washing of the original building makes the building look brand new again.


New kitchen cabinets on Linden in Winnetka. »

September 22, 2017

These are pictures of the kitchen cabinets after installation and a picture of the original cabinets.

 

We have started interior demolition for C.A.R.E. Animal Rescue in Skokie. »

September 21, 2017

We have started to demolish the walls to create the wellness area, real life room and the cat feeding and laudry area.

The exterior is done at our new custom home in Glenview! »

September 19, 2017

We have completed the siding and paver work.  We are starting to landscape now.

The hardwood floors have been stained at 937 Echo Lane. »

September 14, 2017

We have started construction of the 2nd porch on Western Ave in Chicago. »

September 7, 2017

The front door has been installed at our spec house at 937 Echo Lane in Glenview! »

September 6, 2017

Now that the front door and the exterior light fixtures have been installed, we can finish wrapping the columns and complete the siding in the front entry way.

We have started the paver work at our new construction in Glenview! »

September 5, 2017

The driveway is in and we have started the paver work on the front porch and the driveway border.

We have started the finish work at our spec house in Glenview. »

August 29, 2017

We are installing the doors, casing, base and crown moldings.

Demolition of the warehouse is done in Addison »

August 26, 2017

Hardwood floors have been installed at our spec home in Glenview! »

August 26, 2017

We have installed all the hardwood flooring and we are ready to start the finish work (installing doors, casing and baseboards)

The tile is being installed in the bathrooms, laundry room and mud room in Glenview! »

August 25, 2017

We are installing the hardwood flooring at 937 Echo in Glenview! »

August 24, 2017

We are installing 4″ red oak at our spec home in Glenview.

The footings are done for the 2nd porch in Chicago »

August 22, 2017

After the concrete cures, we are ready to begin framing.

We have finished demolition of the 2nd porch on Western Ave. »

August 21, 2017

Starting Demolition on the warehouse on the commercial building in Addison »

August 18, 2017

The roof has been cut so that the demolition can begin to remove 1/2 of the existing warehouse to create 8 store fronts.

 

 

Adding Additional Steel Support to brace the roof in Addison »

August 17, 2017

We are adding additional steel supports to brace the wall and roof since we had to remove a column that was hidden in a wall that was demolished.

The Metal Window Well Grates have been installed at Mango in Morton Grove »

July 30, 2017

The Bathroom Tile Work has been Completed at our Custom Home in Morton Grove »

July 28, 2017

The exterior stonework has been completed at Mango in Morton Grove! »

July 14, 2017

We are tiling the bathrooms at our new construction in Morton Grove! »

July 11, 2017

Fireplace stone work complete at new construction in Morton Grove »

July 10, 2017

The front door installed at Mango in Morton Grove »

July 7, 2017

Starting the bathroom work on the Custom Home in Morton Grove. »

July 6, 2017

We have applied a waterproofing membrane in the showers and have installed the electric floor heat.

 

 

We are installing the hardwood flooring at Mango in Morton Grove. »

June 30, 2017

We are installing Brazilian cherry hardwood throughout the house.

 

The Stone Work on the Bays are done at Mango. »

June 24, 2017

We have installed the Valder’s stone and limestone on the bay areas on our Custom Home in Morton Grove.

 

We have started the Stone Work on the Front of our Custom Home in Morton Grove. »

June 17, 2017

The deck is being framed at our new construction in Glenview! »

August 18, 2017

The First Porch as been completed at Western Ave in Chicago. »

August 11, 2017

We are prepping the garage slab and stoop to pour concrete at 937 Echo Lane Glenview! »

August 10, 2017

The basement walls and floor are done in Winnetka. »

August 4, 2017

We have painted the walls and have put epoxy on the basement floor.  Here are after and before pictures.

We have started framing the porch on Western Ave in Chicago. »

August 1, 2017

The lumber has been delivered and the framing has begun.

The concrete is being poured on our new public sidewalk in Golf! »

July 28, 2017

The old floors have been refinished on the interior remodel in Winnetka! »

July 28, 2017

We have sanded, stained and put 2 coats of polyurethane.  The floors look brand new again!  Here are after and before pictures.

We are completing the water and storm work at our spec house in Glenview! »

July 27, 2017

The fascia and soffits are done at Rollwind in Glenview »

July 27, 2017

We will be ready to install the gutters after the fascia and soffits have been painted.

We will be starting a commercial build out of an animal rescue facility in Skokie soon! »

July 25, 2017

We will be building out an animal rescue and adoption facility for Community Animal Rescue Effort (C.A.R.E.) at their soon to be new location at 4927 Main St. in Skokie.

Interior demolition has started at the 8 storefront build outs in Addison! »

July 24, 2017

We have started to remove all the existing ceiling tiles, electrical conduits and HVAC duct work.

We have started removing the existing soffits and fascia in Glenview. »

July 24, 2017

Footings are poured for the 1st porch on Western Ave in Chicago »

July 24, 2017

We are digging out the old porch footings. »

July 21, 2017

Our new porch will need new larger footings so we are removing the original footings.

We have demolished the 1st porch on Western Ave. in Chicago »

July 20, 2017

The Fire Sprinkler Service has been moved in Addison. »

July 18, 2017

We have moved the RPZ values and have made the new fire sprinkler water connections to the existing Shalimar banquet hall.

Contact Request





News Reviews FAQ Site Map Login