Custom Home Commercial Build Out of Retina Institute of Illinois in Huntley

email a friend Email a Friend»

The cabinets have been installed at Retina Institute of Illinois in Huntley »

August 29, 2019

The vinyl tile is being installed at Retina Institute of Illinois in Huntley »

August 31, 2019

We are grinding the floor prior to installing the vinyl tile at Retina Institute of Illinois »

August 24, 2019

The floors are being prepared for vinyl tile at our eye doctor’s office build out in Huntley »

August 30, 2019

The cabinets and counter tops have been delivered in Huntley »

August 23, 2019

The doors and casings are being installed in Huntley »

August 23, 2019

The sprinkler work is done at our commercial build out of an eye doctor’s office »

August 21, 2019

The walls are being painted at Retina Institute of Illinois in Huntley »

August 21, 2019

The rough electric and HVAC are done and we are ready for above ceiling inspection in Huntley »

August 20, 2019

Drop ceiling grid is done at our commercial build out of the eye doctor’s office in Huntley »

August 18, 2019

The walls are primed and we are ready to start the drop ceilings at Retina Institute of Illinois »

August 13, 2019

We are grinding the floors and leveling them at our Commercial Eye Doctor Build out in Huntley »

August 12, 2019

The walls have been sanded and are ready for priming at Retina Institute of Illinois in Huntley »

August 9, 2019

We are taping and mudding the drywall at Retina Institute of Illinois in Huntley »

August 6, 2019

Drywall has started at our commercial Eye Doctor’s office in Huntley »

August 1, 2019

The rough plumbing, electrical and HVAC are completed at our Retina Institute of Illinois build out »

July 30, 2019

The framing is done and the rough plumbing has started at Retina Institute of Illinois in Huntley »

July 25, 2019

We have started framing the rooms at our commercial Eye Doctor build out in Huntley »

July 23, 2019

The drop ceiling has been removed and the walls are starting to come down at our Retina Institute Build Out in Huntley »

July 12, 2019

The concrete has been poured over the underground plumbing at Retina Institute of Illinois »

July 20, 2019

The underground plumbing is done for the new hand sinks at the doctors office in Huntley »

July 19, 2019

The concrete has been cut so the underground plumbing work can start on our build out in Huntley »

July 18, 2019

The walls have been removed and the floor tiles are being removed at Retina Institute of Illinois in Huntley »

July 15, 2019

Interior demolition has begun in Huntley »

July 12, 2019

The existing drop ceiling is being removed.

We are starting a new commercial build out of Retina Institute of Illinois in Huntley »

July 10, 2019