Foundation walls have been poured at the addition on Kilbourn in Skokie »

April 11, 2018

The crawlspace foundation walls are framed at addition in Skokie »

April 10, 2018

The forms have been set and we are ready to pour the concrete for the foundation walls at Kilbourn.

Footings have been framed and poured at our addition in Skokie »

April 6, 2018

We have poured the footings for the crawlspace addition and have covered the footings with blankets to protect it from the elements.

 

Excavation has begun at the addition on Kilbourn in Skokie »

April 4, 2018

Interior demolition has been completed at our addition in Skokie »

March 30, 2018

We have completed the interior demolition and are now ready to start framing the interior.

The exterior demolition has begun at our addition on Kilbourn in Skokie »

March 29, 2018

The interior demolition has started on our addition in Skokie »

March 27, 2018

We are going to be starting an addition on Kilbourn in Skokie! »

March 24, 2018