Skip to main content
847.410.0620

Commercial & Residential General Contractor



Custom Home   Completed Residential Projects



email a friend Email a Friend»

Slab has been poured and we are ready to frame the basement at our new construction in Lincoln Park. »

February 25, 2017



The Valder Stone delivery from Eden Stone is being unloaded at Mango. »

February 24, 2017



Ready to pour slab in Lincoln Park »

February 23, 2017

The insulation and wire mesh has been installed on the slab floor.  The hydronic tubing has been installed for the radiant heat in the basement slab.  We are now ready to pour the slab at our new construction.



Preparing Basement Slab in Lincoln Park »

February 22, 2017

Adding gravel and leveling out the basement slab at our new construction.



The rough framing has been completed in Lincoln Park. »

February 16, 2017

The rough framing has been completed in Lincoln Park.  The rough HVAC, plumbing and electrical work can begin along with the roofing.



Drying in the roof of our new construction in Morton Grove »

December 23, 2016

Drying in the roof means making it so that water falling on the roof does not penetrate and enter the house.  Since we are going to install Davinci synthetic slate on the roof, a special self adhering membrane underlayment is installed on the roof.



Installing the Pella Windows with the blinds in the glass at Mango »

December 16, 2016



Getting prepared for backfill at the new construction in Lincoln Park »

December 14, 2016

In preparation of backfilling the foundation walls, we are cutting the steel shoring down and are protecting the foundation wall with straw and the ground with blankets so that nothing freezes.

cutting-the-shoring-steel-in-lincoln-park-chicago-1protect-ground-from-freezing-in-lincoln-park-chicago-1protect-concrete-from-cold-in-lincoln-park-chicago-1



Foundation Walls poured and the forms are being removed in Lincoln Park »

December 13, 2016

After we poured the concrete, blankets were put over the foundation walls to keep the warmth in and to allow the concrete to cure in the cold weather.  Once the concrete had cured, the blankets and forms were removed and straw was put around the exterior foundation and blankets were put on the interior ground next to the foundation.  This was done so that the ground doesn’t freeze and we will be able to do the underground and slab plumbing work.

blankets-protecting-foundation-walls-in-lincoln-park-chicago-1removing-the-forms-in-lincoln-park-chicago-1foundation-walls-are-done-in-lincoln-park-chicago-1straw-protects-ground-from-freezing-in-lincoln-park-chicago-1



Setting up the forms for the foundation walls in Lincoln Park »

December 9, 2016

We have set up the forms that frame out the foundation walls at the new construction in Lincoln Park.  We are ready to pour the concrete. setting-up-the-wall-forms-in-lincoln-park-chicago-1ready-to-pour-the-foundation-walls-in-lincoln-park-chicago-1

 



Setting up and pouring the footings in Lincoln Park Chicago »

December 8, 2016

The purpose of the footings is to support the foundation and prevent settling.  They are first framed with wood and then the concrete is poured and smoothed out.  The foundation walls will be built on top of the footings.

framing-the-footings-in-lincoln-park-chicago-1pouring-the-footings-in-lincoln-park-chicago-1pouring-the-footings-in-lincoln-park-chicago-1-2



Excavating so that we can start building the custom home in Lincoln Park Chicago. »

December 7, 2016

Since the houses are so close in Chicago, we had a settlement surveyor come out to set up control points on the neighbors house.  These control points will be measured again after the foundation has been back filled to show that there was no settlement of the buildings next to the construction site.  We then we used steel beams to shore the banks.  The shoring (steel beams) supports the dirt so that it doesn’t collapse into the newly excavated foundation.  Once the shoring has been installed, the excavation can be done without having to worry about the banks collapsing.

excavating-for-foundation-in-lincoln-park-chicago-1shoring-the-banks-in-lincoln-park-chicago-1finishing-excavation-in-lincoln-park-chicago-1



Building the Oval Ceiling in the foyer to showcase the chandelier »

December 6, 2016



Building the roof at Mango in Morton Grove »

December 4, 2016

After the framing of the 2nd floor ceiling joists the roof rafters and plywood are installed.



Pouring the basement slab in Morton Grove »

November 29, 2016

We have installed the radiant tubing over the wire mesh in the basement and are now pouring the concrete for the slab.



Knocking down the walls and removing the debris in Lincoln Park »

November 26, 2016

 

All of the building materials have been donated.  Now it is time to knock down the walls and remove the construction debris so that we can start excavation.

demo-brick-walls-lincoln-park-chicago-1 removing-debris-lincoln-park-chicago-1



Materials are being set aside for donating at the Lincoln Park Chicago Project »

November 22, 2016

The roof and 2nd floor have been deconstructed and broken down in the materials that will be donated.  The next step is to deconstruct the first floor and the basement.

 

cinder-blocks-and-brick-left-lincoln-park-chicago-11st-floor-left-to-demo-lincoln-park-chicago-1deconstruction-done-lincoln-park-chicago-1



Raising the second floor walls at Mango »

November 22, 2016



Building second floor walls at the new construction in Morton Grove »

November 21, 2016



Deconstruction in Lincoln Park Chicago »

November 18, 2016

The owners have decided to have their home deconstructed instead of demolished.  Deconstruction is the process of taking down the house in the reverse order of how it was built and then donating the building materials to charities like Habitat for Humanity.  Deconstruction is done by hand instead of using heavy equipment to preserve the materials.  The cost is a higher than having the house demolished, but there are tax deductions for the donations that help offset the higher costs.

demolition-in-lincoln-park-chicagodemo-material-inside-lincoln-park-chicagodeconstruction-in-lincoln-park-chicago



The second floor deck has been built in Morton Grove. »

November 18, 2016

The second floor deck is has been built at Mango in Morton Grove.



The basement slab is ready for radiant heat tubing to be installed at Mango »

November 15, 2016

The underground plumbing has been completed and inspected.  Then crushed gravel was spread evenly over the whole basement floor and the insulation/vapor barrier has been laid over the gravel and taped.  Then we installed a concrete reinforcement mesh on the top.  Now we are ready for the radiant heat tubing to be installed.



Building the first floor interior walls at new construction in Morton Grove »

November 14, 2016

We are raising the interior first floor walls at Mango.  The walls are built on the ground and then lifted into place and nailed.



Building the first floor walls in Morton Grove »

November 10, 2016

We are framing the first floor walls at the new construction at Mango.

 



Framing the first floor decking at Mango »

November 7, 2016

The framing has started and the framers are working on the first floor decking.  Once the first floor decking has been completed they can start to build the walls.

first-floor-decking-in-morton-groveframing-the-first-floor-decking-in-morton-groveframing-new-construction-mango



Installing Steel Beams and Columns in Morton Grove »

November 5, 2016

We are installing the steel beams and columns at Mango so that we can start framing the new construction.

crane-with-steel-at-new-constructioninstalling-steel-in-morton-groveinstalling-steel-at-mango



Waterpoofing the foundation at Mango in Morton Grove »

November 4, 2016

We are applying the Rub-R wall product to waterproof the foundation walls.  When the Rub-R wall product is used, the company warrants all the areas covered by the Rub-R wall product not to leak for the life of the foundation.   For more information about this product, you can go to http://www.westsiderubrwall.com/

spraying-rub-r-wall-on-foundationrub-r-wall-application-on-mangofoundation-waterproofing-morton-grove



Pouring the foundation walls at Mango in Morton Grove. »

November 3, 2016

We have installed horizontal and vertical rebar inside the form walls before we pour the concrete to make the walls stronger and are pouring 4000 PSI concrete.

rebar-foundation-mango-morton-grove-1pouring-foundation-mango-morton-grove-1foundation-walls-mango-morton-grove-1



Building the foundation walls before pouring the concrete at Mango in Morton Grove »

November 1, 2016

The forms were lowered into the basement and now they are being installed so that the concrete foundation walls can be poured.

mango-morton-grove-formsmango-morton-grove-framing-foundation-wallsmango-morton-grove-framed-and-ready-for-inspection



Coming Soon – New Construction in New Trier Township Glenview! »

October 30, 2016

We will be starting construction on a home in the New Trier school district. It is not too late to make some changes during construction.  More information coming in the next few weeks.

new-construction-glenview-coming-soon



Installing the Drain Tile at Mango in Morton Grove »

October 29, 2016

Drain tile is a corrugated pipe with small slits covered with a fabric sleeve.  The drain tile is then covered with gravel.  The slits let water enter the pipe and the fabric sleeve prevents larger soil objects to enter the pipe.  The purpose of the drain tile is to collect the water around the basement foundation and divert it to the sump pump pit and then it is pumped out of the house and away from the foundation.

mango-morton-grove-drain-tilemango-morton-grove-drain-tile-installationmango-morton-grove-gravel-and-drain-tile



We have framed and poured the footings at Mango in Morton Grove »

October 28, 2016

We had the inspection from the Village of Glenview on the footings prior to pouring the concrete and got the green light so we poured the concrete.  The next step will be to frame the foundation walls and schedule a pre-pour inspection.

mango-morton-grove-footingsmango-morton-grove-framing-the-footingsmango-morton-grove-pouring-the-concrete-footings



The Park Ridge Pergola is done! »

October 27, 2016

We have completed the Pergola and all the patio furniture has been moved back.  The trim on the columns is a great touch to dress up what would have been plain wood columns and add some dimensions to the pergola.

completed-pergola-park-ridgeoutdoor-pergola-park-ridgecompleted-pergoal-roof-park-ridge



We are starting Construction on a New Custom Home in Lincoln Park, Chicago »

October 26, 2016

We are waiting for the water to be disconnected at the street and the City of Chicago permits, once we have that done we will be at full speed ahead to get the foundation poured before the winter sets in.

new-construction-lincoln-park-chicago

 

 

 

 



Work Continues on New Construction in Swainwood subdivision Glenview »

October 16, 2016

The plumber, electrician and HVAC contractors have started to do the rough in work.  This means that the lines for plumbing, electrical and HVAC are brought into the house and into each room but the final connections are not made.  After all the rough in work has been completed, the Village of Glenview will come out to inspect the work.

plumbing-new-construction-glenviewelectrical-new-construction-glenviewhvac-new-construction-glenview



Excavation on Mango in Morton Grove »

October 12, 2016

Demolition has been completed and excavation has started on our new construction in Morton Grove.  During excavation, the banks need to be protected so they don’t collapse so plywood and steel is used to shore the banks.  The shoring is covered with heavy plastic to protect the banks from any erosion by heavy rains.
morton-grove-excavationmango-morton-grove-excavation-and-shoring



Pergola in Park Ridge has been Framed »

October 11, 2016

The framing has been completed on the pergola.  The last step will be to trim the columns and do the paint touch ups and caulking.  Then schedule the final inspection with the City of Park Ridge.

framing-pergola-park-ridgeinstalling-joists-pergola-park-ridgefinishing-up-framing-pergola-park-ridge



In Park Ridge, the pergola is ready to be framed »

October 9, 2016

The masons have rebuilt the walls after the posts/columns have been anchored to the footing. The next step will be to frame the Pergola and then add the finishing trim.

rebuilding-patio-wall-outdoor-structurepatio-wall-completed-outdoor-structureready-to-build-pergola-outdoor-structure

 



Demolition has begun on Mango in Morton Grove today! »

September 30, 2016

We have torn down the first house and will start start tearing down the second house this coming week.  It is amazing how a house can be demolished in about a day and it takes many months to build.

mango-morton-grove-demolition-2mango-morton-grove-demolitionmango-morton-grove-demolition-3



We have started construction of the custom Pergola in Park Ridge »

September 28, 2016

The architectural plans were approved by the City of Park Ridge and we have started construction.  The first step is for the mason to cut the existing stone walls to allow for the pergola columns to be secured to the concrete foundation.

patio-wall-masonry-work-in-progress-outdoor-structure-constructionpatio-wall-masonry-demolition-outdoor-structure-construction patio-wall-ready-for-post-installation-outdoor-structure-contruction

 



The framing has been completed on our new construction in Glenview »

September 12, 2016

Now that the framing has been completed we can start working on the roof, rough electrical, rough HVAC and rough plumbing.
2016-08-06 08.34.52
Walls-New-Construction-Project-in-Glenview.Walls-New-Construction-Project-in-Glenview.



The foundation slab has been poured on our new construction in Glenview »

September 5, 2016

Now that the foundation has been completed and the slab has been poured, we can start framing next.

2016-07-28 10.01.41 2016-07-28 10.01.36



We will be starting demolition of two houses on Mango Ave. in Morton Grove »

August 9, 2016

We will be starting demolition of two houses that will become one new custom home in Morton Grove in the next couple of weeks.  More pictures to follow during the construction of the new house.

Mango Morton Grove Site for New Construction - side view Mango Morton Grove Site for New Construction



The Rub-R-Wall Product has been applied to the Foundation Walls on the New Construction Project in Glenview »

July 26, 2016

In Glenview, the Rub-R-Wall product has been applied to the foundation walls. This product is great and gives a lifetime warranty against water leakage for all the areas covered by the product.

You can see the product at http://www.westsiderubrwall.com/. The steel has been installed and we are now ready for backfill.

The Rub-R-Wall product for the foundation walls The Rub-R-Wall product has been applied to the foundation walls-in-Glenview0Custom-Home-Project The Rub-R-Wall product has been applied to the Custom Home foundation



The Foundation Walls are done on our Glenview project »

July 8, 2016

Next up measuring for steel and rubber waterproofing of the foundation walls.

The Foundation Walls are done on our Custom Home Construction Project in Glenview, IL The Foundation Walls are done on our Custom Home project in Glenview



Excavation is done, the footings have been poured and we are getting ready to frame the walls on our Glenview project »

July 5, 2016

getting ready to frame the wallsgetting ready to frame the walls on our Glenview projectEcavation is done, the footings have been poured and we are getting ready to frame the walls on our Glenview project



Our Home Addition in Chicago is Nearing Completion »

June 27, 2016

Our addition in Chicago is nearing completion, we have installed the cabinets and are starting to paint. The landscaping has been done and there is only the deck left.

home-addition-in-chicago-kitchen-almost home-addition-chicago-progresshome-addition-chicago-back



We have started a New Construction Project in Glenview »

June 22, 2016

Stay tuned for updates as the project moves along.

New Construction Project in Glenview - Demolition Work New Construction Project in Glenview - Demolition New Construction Project in Glenview.

 



Finished Pouring the Footings and Walls at the Chicago Addition Construction »

December 26, 2015

Finished pouring the footings and walls at the Chicago addition Home-Addition-in-Chicago-Finished-pouring-the-footings-and-walls



We have Started Excavation at the Chicago Addition Construction Project »

December 11, 2015

We have Started Excavation at the Chicago Addition Construction Project Home Addition in Chicago-We have started excavation



Home Addition in Chicago “Before” Pictures »

December 8, 2015

We are starting work on an addition in Chicago and here are the before exterior pictures.

BackHome Addition in Chicago - front view











back



News Reviews FAQ Site Map Login