Skip to main content
847.410.0620

Commercial & Residential General Contractor



Custom HomeHome Addition on Kilbourn in Skokie



email a friend Email a Friend»

Kilbourn in Skokie – Completed Addition – Gallery »

August 20, 2019


Kilbourn in Skokie – Completed Addition – Gallery - Builders News 4462 View Completed Project Gallery


Stain and final coat on the basement stairs at the addition on Kilbourn »

April 22, 2019



Painting has been completed at Kilbourn in Skokie »

March 19, 2019



Installing the new basement stairs at our addition on Kilbourn in Skokie »

March 4, 2019



Installing Kitchen back splash tile at the addition in Skokie »

February 1, 2019



The cabinets are being installed in the kitchen at Kilbourn in Skokie »

November 9, 2018



The front door and roof gable has been completed at Kilbourn in Skokie »

October 18, 2018



Hardwood floors are being installed at our addition in Skokie »

October 11, 2018



The tile work has begun at our addition in Skokie »

October 5, 2018



Drywall has been hung, taped and primed at the addition on Kilbourn in Skokie »

August 27, 2018



Masonry work and landscaping done at our addition in Skokie »

August 21, 2018



New roof over front door at the addition on Kilbourn in Skokie »

July 18, 2018

The owners have decided they want an roof overhang over the front door.

 



We are using Closed Cell spray foam insulation at Kilbourn in Skokie »

July 17, 2018



We are preparing the basement walls for insulation at the addition in Skokie »

June 1, 2018



Finished the flat work at our Addition in Skokie »

May 18, 2018

We poured the concrete sidewalks and patio slab.



New Water Service for our addition in Skokie »

May 16, 2018

We have to bring a new water line in from the City main to the house for the addition.



Patio slab and side walks are being prepped at our addition on Kilbourn in Skokie »

May 10, 2018

We are putting down the stone and wire mesh to prep the patio slab prior to pouring the concrete along with prepping the sidewalks.



Architectural Shingles are being installed on the Roof at Kilbourn in Skokie »

May 8, 2018



Roof framing at the addition on Kilbourn in Skokie »

April 27, 2018



Framing the roof at Kilbourn in Skokie »

April 24, 2018



Framing of the new addition has begun at our addition in Skokie »

April 21, 2018

The sub floor has been built on top of the foundation wall and the wall and roof framing can begin.



Interior Framing of the existing house has begun on the addition in Skokie »

April 17, 2018



Pouring the slab at the addition on Kilbourn »

April 17, 2018



Getting the base prepared for the slab to be poured at the addition in Skokie »

April 13, 2018

There is a thick layer of stone followed by the plastic and then a wire mesh on top.  This is the base for the concrete slab.



Foundation walls are being damp proofed at the addition in Skokie »

April 12, 2018

The forms are being removed on the foundation walls and the exterior walls are being damp proofed.



Foundation walls have been poured at the addition on Kilbourn in Skokie »

April 11, 2018



The crawlspace foundation walls are framed at addition in Skokie »

April 10, 2018

The forms have been set and we are ready to pour the concrete for the foundation walls at Kilbourn.



Footings have been framed and poured at our addition in Skokie »

April 6, 2018

We have poured the footings for the crawlspace addition and have covered the footings with blankets to protect it from the elements.

 



Excavation has begun at the addition on Kilbourn in Skokie »

April 4, 2018



Interior demolition has been completed at our addition in Skokie »

March 30, 2018

We have completed the interior demolition and are now ready to start framing the interior.



The exterior demolition has begun at our addition on Kilbourn in Skokie »

March 29, 2018



The interior demolition has started on our addition in Skokie »

March 27, 2018



We are going to be starting an addition on Kilbourn in Skokie! »

March 24, 2018











back



News Reviews FAQ Site Map Login